On November 23, 2026, at the Cité Internationale Universitaire in Paris, the Ministry of the Economy presented the second edition of Choose France dedicated to French companies investing in the country. The Bercy press kit lists 273 projects carried out by 253 companies, for 42.5 billion euros. Digital comes second among the sectors, with 40 projects. The only digital infrastructure project that the document estimates in the billions, the Orange and Morrison data center joint venture, was nevertheless made public on July 27, and its documentation has not yet been signed.
81 new projects out of 273, without mention to recognize them
The file itself gives the key to reading the total. Of the 273 announcements, 192 were already known. The 81 projects presented as new represent nearly 14.9 billion euros, or 35% of the envelope. The remaining 27.6 billion correspond to investments made public earlier. In terms of amount, the proportion has changed little in one year: according to the same document, the November 2025 edition included 151 projects for 30.4 billion euros, including around thirty new projects for around 10 billion.
Two programs dominate the bill. The ADP group plans 9.5 billion euros for the overhaul of Paris-Charles-de-Gaulle and Paris-Orly airports, “subject to approval by the board of directors”, specifies the file. RTE, the electricity transmission network manager, accounts for 8 billion, according to Reuters, which relayed on November 22 the elements communicated by the Élysée. Together, they weigh 17.5 billion, more than all the money presented as new. At least part of these two programs therefore falls under previous announcements.
The document does not say which one. As of November 24, the file posted online by Bercy classifies the companies by region and describes some of the projects, but no file contains the explicit mention “unpublished” or “already announced”. The amount of RTE does not appear there either, the network manager not having a project sheet.
Forty digital projects, eight figures
Digital goes from 28 projects in 2025 to 40 in 2026, behind energy and environmental transition (67 projects). Bercy does not publish any amount by sector. The “digital sovereignty” chapter of the file describes eight projects, the total amounts of which reach approximately 3.3 billion euros. Orange alone represents 3 billion.
The other seven files range from 5 to 175 million euros. Qonto announces 175 million and 300 recruitments by the end of 2027, after obtaining its credit institution approval. Calcore plans 110 million for a data center in Normandy, Kiro a program of more than 17 million supported by France 2030, Eridanis around 10 million over three years. Three fundraisings of 5 to 9 million followed (Kwan-tek, NPco, Faactopi). The regional list cites other industry names, including Etix Everywhere, Eclairion, NumSpot, Probabl, Gradium, Quandela and Quobly, without description or amount on file.
Orange and Morrison: 400 MW targeted, an exclusivity agreement at this stage
The heaviest project of the chapter was not born at the top. Orange’s press release dates from July 27, 2026 and announces the signing of an exclusivity agreement with the investment company Morrison, with a view to creating a data center joint venture located in France and co-controlled by the two partners. The text describes the operation in the conditional, and the Bercy file uses the formula: the partnership “would constitute” a strategic investment.
Orange would bring five data centers spread over four campuses (Chevilly-Larue, Aubervilliers, Chartres and Val-de-Reuil). The target capacity is 400 MW, “nearly ten times the current capacity”. The 3 billion euro program would be based on “Orange’s existing assets, Morrison’s equity contribution and debt”: the figure therefore combines assets already built and capital to be raised. Orange Business would be the exclusive marketing partner for colocation and accommodation offers.
The signing of the documentation “should take place by the end of 2026”, subject in particular to consultation with staff representative bodies and regulatory authorizations. Completion is expected in the first quarter of 2027. The government nevertheless put the file forward on November 23: the minister responsible for AI and Digital Technology, Anne Le Hénanff, visited that day the Orange data center in Amilly, near Chartres, where four new rooms were added, two of which were already full, reports L’Écho Républicain.
Calcore and Etix Everywhere, the announcements of the day in data centers
The second data center in the file is of another size. Calcore announces 110 million euros for a “high intensity” site in Normandy, supplied by a long-term supply contract from a neighboring biomass plant. The file gives neither power nor timetable. Capital mentions 20 MW and delivery expected in early 2028.
A third project was costed the same day by its leader. In a press release reproduced by DCmag, Etix Everywhere announces 100 million euros to add 12 MW to its local data centers in Île-de-France, Hauts-de-France and Occitanie. The operator specifies that 50 million comes from a refinancing announced in September 2025, the rest being provided in equity. Half of the amount had therefore already been made public.
On the usage side, Kiro is launching OPTIMABIO with the AP-HM, the Hospices Civils de Lyon and the Limoges University Hospital, to develop an AI to help prescribe biological examinations. Crédit Agricole announces that it has selected the start-up Prisme.ai as a technological partner to deploy AI agents connected to its information system, without disclosure.
400 MW for Orange, 3.1 GW for the first phase of SoftBank
Comparison with the international edition of June 1, 2026 gives the scale. In Versailles, 93 billion euros had been displayed, including 45 billion firm for the first phase of SoftBank in Hauts-de-France, or 3.1 GW by 2031. The 400 MW targeted by Orange and Morrison represent around an eighth of this single tranche. The November 23 file recalls the order of magnitude: more than 180 billion euros of investments in data centers claimed since the Summit for Action on AI in February 2025, where 109 billion were announced for AI, and the 2025 and 2026 editions of Choose France. It also indicates that the projects in development have secured 25 GW of electrical power from RTE.
The rapprochement also applies to the needs that the executive itself formulates. In a video published on November 15, Emmanuel Macron wanted to “acquire himself with a gigawatt before the end of 2028”, computing capacities which according to him should allow Mistral AI to remain in the competition, or “50 billion euros approximately over five years”, according to the transcription given by Next. Mistral AI does not appear in the list of companies published by Bercy.
The November 23 showcase describes a fairly clear sharing of roles. According to the announcements recorded since February 2025, the capital which finances computing power in France comes mainly from abroad, including in the Orange project, backed by an asset manager founded in New Zealand. French companies mainly bring sites, existing assets and use cases. For a trusted buyer of hosting or cloud capacity, there are three data center projects encrypted on this occasion. Only one exceeds a hundred megawatts, and it dates from July.
End of 2026, beginning of 2027, beginning of 2028: the calendar of announced projects
The closest deadline is Orange and Morrison, who plan to sign before the end of the year. ADP is awaiting the green light from its board of directors for its 9.5 billion and, according to Capital, the signing of its regulatory contract with the State. Delivery of the Calcore Normandy site is expected in early 2028, again according to Capital. As of November 24, the Bercy file still does not make it possible to isolate the 81 unpublished projects.